Project Details
R.J. Forbes worked with Vistra at its combined-cycle power plant in Bellingham, Massachusetts, to restore the protective coating on a flue-gas stack. The existing coating was delaminating, leaving the upper 80 feet of steel exposed to the elements.
Project Challenge
The stack was almost continuously online, creating a hot substrate that complicated surface preparation and coating selection. Access at height was difficult, and the plant needed a gray finish suitable for the application conditions. The work plan had to account for operating temperatures as well as the practical limitations of reaching the affected steel.
Project Solution
We evaluated options ranging from crane-and-basket access to robotic preparation, along with water jetting, vacuum blasting, and different coating technologies. The plant selected scaffolding access with surface preparation and coating application performed while the stack remained online.
Our crew used abrasive blasting to remove failing coatings and prepare the steel. Working with Dampney Coatings, we selected a hot-applied silicone copolymer direct-to-metal coating for the conditions. This coordinated approach restored protective coverage without requiring the stack to be taken offline for the coating work.
This flue-gas stack recoating project brings together abrasive blasting, high heat coating for the power generation sector.